Do You Need a Permit to Clear Land in Georgia?

For most single home lots, no. Georgia’s erosion law does not apply to a project that disturbs less than one acre. That exemption ends inside a larger development plan of one acre or more. It also ends within 200 feet of the bank of a creek or other state waters.

Past those lines, a land disturbance permit comes into play unless another exemption fits. At one acre or more, a construction stormwater permit from the Georgia Environmental Protection Division (EPD) applies too. Farm and forestry work have their own exemptions. Burning the piles is a separate step with the Georgia Forestry Commission, and machine digging needs a Georgia 811 ticket.

The county or city office has the last word for your lot. A local issuing authority may still regulate small projects the other exemptions leave out. Southern Grind Solutions does land clearing around Broxton. This guide is education on the law and agency rules, not legal advice.

Here are the permits and steps in one place.

Permit or stepWhen it appliesWho issues it
Land disturbance permitOne acre or more, a larger common plan, or within 200 feet of state waters, unless another exemption fitsThe county or city, where it is a local issuing authority
EPD stormwater Notice of IntentOne acre or more; coverage starts 14 days after the NOI is submittedFiled with Georgia EPD
Burn permitLand clearing burns need a permit or notice; hand-piled yard debris needs noneGeorgia Forestry Commission, 1-800-GA-TREES or online
Georgia 811 ticketDigging or pulling stumps with a machine, at least 3 business days aheadGeorgia 811, online or by dialing 811
Section 404 permitDredged or fill material going into wetlands or other waters of the United StatesU.S. Army Corps of Engineers
Septic permitA new house or mobile home that will use a septic systemThe county health department

When does Georgia require a land disturbance permit?

Georgia’s Erosion and Sedimentation Act covers land-disturbing activity. The law’s definition names clearing, dredging, grading, excavating, transporting and filling of land. So clearing land counts, unless an exemption fits.

The biggest exemption is size: a project with less than one acre of disturbed area. It does not cover a lot inside a larger common plan of development of one acre or more. It also does not apply within 200 feet of the bank of any state waters.

For that 200-foot rule, the law leaves out channels and drainageways that carry water only during and right after rain. It also leaves out intermittent streams that are not wet year round. Within 200 feet of one, a project under one acre must still keep its sediment on the property.

Where a county or city runs the program as a local issuing authority, the permit comes from its office. Ask the county office, or the city office if the lot is inside city limits.

What land clearing is exempt?

These exemptions matter most for clearing land:

  • One house on less than an acre. Building one single-family house is exempt when it disturbs less than one acre outside a larger common plan. It must still meet the act’s minimum requirements.
  • Farm work. Agricultural operations are exempt. The law names preparing and planting pasture land, and farm ponds.
  • Forestry. Forestry land management practices, including harvesting, are exempt.

Forestry has a catch. If that work disturbs a stream buffer, the whole property is limited to normal forest management for three years after. Plan any house site before the timber comes off.

The law also sets a 25-foot buffer along the banks of all state waters, with listed exceptions. It is measured horizontally from the point where normal stream flow has wrested the vegetation from the bank.

What changes at one acre or more?

EPD’s construction stormwater general permit covers land disturbance of one acre or more. For a stand-alone project, that is permit GAR100001.

Coverage under that permit starts with a Notice of Intent, or NOI. It begins 14 days after the NOI is submitted and its submittal is confirmed. Plan for that wait. For what the clearing itself costs, see the guide to land clearing cost per acre.

Do you need a permit to burn brush piles in Georgia?

It depends on the pile. Georgia’s outdoor burning rules changed on July 1, 2021. Hand-piled yard debris now needs no permit, and that means leaves and limbs only.

Land clearing burns call for notifying the Georgia Forestry Commission or getting a burn permit from it. The permit comes by phone at 1-800-GA-TREES or online. It is good only for the day it is issued.

Debris from machine clearing counts as a land type change under EPD’s land clearing burning rules. Depending on the county, it may require an air curtain destructor.

EPD’s summer burn ban runs May 1 to September 30 in 54 northern Georgia counties. Burning man-made materials is unlawful in Georgia, even in a burn barrel. That covers tires, shingles, plastics, lumber and household garbage.

If the piles get burned, the Forestry Commission comes first. Forestry mulching leaves no pile to burn. It grinds brush and small trees in place and leaves the mulch on the ground.

Do you need to call 811 before clearing land?

If a machine will dig, yes. Georgia’s dig law calls it excavating when mechanized equipment moves earth or rock below grade. Pulling stumps with a machine does that.

Georgia 811 asks for a ticket at least 3 business days before digging. You can submit one online or dial 811. Whoever operates the equipment is the one digging.

The law calls any person engaged in excavating an excavator. Machine digging cannot start until the person planning it has submitted a locate request.

What about wet ground and wetlands?

Clean Water Act Section 404 requires a permit before dredged or fill material goes into waters of the United States. Wetlands are included. Certain farming and forestry activities are exempt.

The U.S. Army Corps of Engineers runs the program day to day, including permit decisions. Ask the Corps before any grading or filling on wet ground.

What if the cleared lot is getting a septic system?

Under Georgia’s rules, a house on septic needs a construction permit from the county health department. The rules bar physical development of the lot until then. Yet the Southeast Health District’s application, used in Coffee County, asks whether the site is cleared. Ask the county health department what clearing it wants first.

Our septic tank permit guide covers the rest of that application. Southern Grind Solutions does septic tank installation for new houses and mobile homes. Our site preparation work puts the clearing, the rough grade, the pad and the septic system into one job.

How do you get a land clearing quote around Broxton?

Southern Grind Solutions clears overgrown lots and acreage, fence lines, brush and small trees about 80 miles around Broxton. That covers clearing for a house site or a mobile home site. Check with the county or city office about permits for your lot before the work starts.

We look at the job and put the quote in writing. Read more about land clearing around Broxton, or call or text (912) 381-6261.

Frequently asked questions

Do I need a permit to clear less than an acre in Georgia?
Often not under the state's erosion law, which does not apply to a project that disturbs less than one acre. That exemption ends within 200 feet of the bank of state waters. It also ends inside a larger common plan of development of one acre or more. A local issuing authority may still regulate a small project no other exemption covers, so ask the county or city office.
Are there rules for clearing land near a creek in Georgia?
Georgia's erosion law sets a 25-foot buffer along the banks of all state waters, with listed exceptions. It is measured horizontally from the point where normal stream flow has wrested the vegetation from the bank. The small-project exemption also ends within 200 feet of state waters. Ask the county office before clearing near a creek.
Do farmers need a permit to clear land in Georgia?
Georgia's erosion law exempts agricultural operations, including preparing and planting pasture land and farm ponds. Federal Section 404 also exempts certain farming and forestry activities. Machine digging on a farm, beyond tilling fields, still needs a Georgia 811 ticket. Ask the county office if the work goes beyond farming.
Is a timber harvest exempt from Georgia's erosion law?
Yes, forestry land management practices, including harvesting, are exempt. If that work disturbs a stream buffer, the whole property is limited to normal forest management for three years after. Plan any house site before the timber comes off.
How long is a Georgia burn permit good for?
Only for the day it is issued, according to the Georgia Forestry Commission. Land clearing burns need that permit or notice to the commission, by phone at 1-800-GA-TREES or online. Hand-piled yard debris, meaning leaves and limbs only, needs no permit.
How far ahead should you call 811 before pulling stumps?
Georgia 811 asks for a ticket at least 3 business days before digging. You can submit it online or dial 811. Pulling stumps with a machine moves earth below grade, which is excavating under Georgia's dig law.
Is this what Southern Grind Solutions charges?
No. This page covers the state's permit rules, not our price list. We look at the job and put the quote in writing. Call or text (912) 381-6261.
Request a Quote

Get In Touch With Southern Grind Solutions

Building a house or moving into a mobile home? Call or text (912) 381-6261 or use the form, and tell us which county the job is in.

Request a Quote

Tell us about the new septic system, the land to clear or the dirt work and where it is. We look at the job and put the quote in writing.

Call (912) 381-6261