Septic Tank Permit in Georgia: How Do You Get One?

In Georgia, a septic tank permit is a construction permit from the county health department. A new system needs one before any work starts on the lot. The owner, or an agent for the owner, applies in writing on the county’s form. The county issues the permit only after a site inspection finds the soil, the groundwater and the rock favorable.

The county has 20 days after a complete application to approve or deny it. In the Southeast Health District, which covers Coffee County, the permit expires 12 months from the date of issue. Nothing gets covered or used until the county makes a final inspection and approves the system in writing. Southern Grind Solutions does septic tank installation for new houses and mobile homes around Broxton.

Who issues a septic tank permit in Georgia?

The county health department issues it, under the Georgia Department of Public Health’s septic rules, Chapter 511-3-1. In the Southeast Health District, every county health department has at least one environmental health specialist.

The permit comes from the county where the lot sits. For a lot in Coffee County, that is the Coffee County Health Department at 1111 West Baker Highway in Douglas. For a lot in Wayne County, it is the county health department in Jesup.

What does the septic permit application ask for?

Georgia’s rules list what the application includes:

  • The owner’s name and address, and the applicant’s, if that is someone else.
  • Where the property is, and a plan showing the system’s location and design, with drainage and piping.
  • Every water supply, geothermal borehole, utility or trash pit that bears on where the system goes.
  • The number of bedrooms.
  • The soil, the seasonal high groundwater and any rock.
  • The signature of the owner or the agent applying.

The Southeast Health District’s standard form asks for more. It wants the bedroom count, stick built or mobile home, and the foundation. It asks about the water supply: public, a private well or a community system. It asks whether the house site is staked and whether the site is cleared. An unstaked house site can mean a reevaluation fee.

The form also wants a site sketch. It shows the building, the road, the well, the proposed tank and drain field, and the driveways, sheds and barns. The form advises checking local zoning and covenants first. In Lowndes County, the posted process asks for a letter of approval from the county zoning office.

What does the county check before it issues the permit?

The county’s site inspection has to find favorable absorption rates, soil, groundwater and rock. Soil evaluations are done by people the Department of Public Health certifies. For the soil test itself and getting the lot ready for it, see the perc test guide.

Planning to fill or reshape the lot so it can pass? The rules want plans for that work sent to the county first. No changes may start before the county approves those plans.

How long does a septic permit take, and how long does it last?

Georgia’s rules give the county 20 days after it receives a completed application to approve or deny it. Ask the county office how soon it can visit the lot.

Statewide, a construction permit stays valid for no more than 12 months from the date of issue. The Southeast Health District’s form says its permit expires 12 months from the date of issue. Plan the install inside that window.

What happens during the install?

Georgia’s rules say a septic tank contractor must hold a current certification from the Department of Public Health. The only other way is to work under the on-site supervision of someone who holds one. That certification is renewed every two years and depends on continuing education.

The installer builds the system to the permit and the submitted site plan. The district’s form makes the installation contractor responsible for setbacks. Those are the distances from wells, wetlands, bodies of water, structures and property lines.

When construction is done, and before final cover, the owner or the owner’s contractor tells the county health department. No one may backfill or use the system until the county inspects it and approves it in writing. A copy of the final inspection report goes to the owner, builder, developer or agent.

What can void a septic permit or the final approval?

The district’s form names two risks to a permit. Grading, filling or other landscaping after the permit is issued may void it. Not following the submitted site plan may void it too. The county can also deny or revoke a permit when the lot is unsuitable or the rules are not followed.

The final approval has its own limits. Grading, filling, trash pits or other work on the lot that may harm the system voids it. Removing or changing parts of the system after the final inspection voids it too.

So put the house, the driveway and any sheds on the site sketch from the start. Site preparation for a new house or mobile home covers the clearing, the rough grade and the pad. The septic system can be part of the same job.

Does a mobile home need a septic permit?

Yes. A mobile home on a lot without sewer needs the same construction permit as a house. The district’s form covers both, with one box for stick built and one for mobile home. Georgia sizes the tank by bedrooms, not by the type of home. One to four bedrooms take 1,000 gallons, plus 250 gallons for each bedroom over four.

A mobile home pad is built-up fill, and the form says filling after the permit is issued may void it. Show the pad on the site sketch, and ask the county how its timing fits the permit.

Do septic repairs need a permit too?

Yes. Georgia’s rules say repairs, replacements and additions to existing systems must be permitted and inspected. The Southeast Health District’s form covers a new system permit, a repair permit and an existing system evaluation. In Lowndes County, the posted repair site evaluation and permit fee is $180, due when you apply.

Southern Grind Solutions installs new septic systems only. Septic repairs go to another company.

What does a septic permit cost in Georgia?

The county health department sets and quotes its own fee, so ask the office in the lot’s county. Lowndes County, in the South Health District, posts its fees:

  • New system: $240 for the site evaluation and the permit, due when you apply. The fee sheet splits it into $120 for each.
  • The install inspection: included in the $120 permit fee.
  • Another inspection trip: $120 when an install needs more trips to correct faults in construction.
  • A filled site: $200 to certify fill material where the drain field design calls for fill.

These are Lowndes County’s posted fees, not a statewide figure and not our price list. For what the system itself costs, see the septic cost guide.

How do you get a written quote for a new septic system?

Southern Grind Solutions installs new septic tanks and drain fields about 80 miles around Broxton, Georgia. The work covers the dig, setting the tank, the drain field lines, backfill and rough grade. The county’s permit sets the design for your lot.

We look at the job and put the quote in writing. Our page on new septic tanks and drain fields around Broxton covers the work. Call or text (912) 381-6261.

Frequently asked questions

Who can apply for a septic permit in Georgia?
The owner, or an agent applying for the owner. Georgia's rules call for the owner's or the agent's signature on the application. The application names the owner, and the applicant too when that is someone else.
Do I need a septic permit if city sewer is close by?
You may need to hook up to the sewer instead. Georgia's rules require a sewer hookup when public or community sewer is available within 200 feet of the property line. A sewer in a public right-of-way along the property counts too. Where no sewer is available, the home needs an approved septic system, and that takes the permit.
Can work start on the lot before the septic permit is issued?
Georgia's rules bar the physical development of a lot that will use septic until the permit is issued. Plans to fill or reshape the lot to qualify need the county's approval first. Ask the county health department what it wants done before its visit, such as staking the house site.
Can the site plan change after the permit is issued?
Talk to the county health department before anything moves. The Southeast Health District's form warns that deviations from the submitted plan could bring permit denial or revocation. Moving the house, the well or the drain field changes what the county approved.
What paperwork comes with a finished septic system?
A copy of the county's final inspection report goes to the owner, builder, developer or agent. Georgia's rules also have the installer give the owner a notice of the system's type, design and maintenance needs. For a newly built home, the builder or contractor gives that notice to the new owner at the sale.
Is the septic permit the only permit a lot needs?
It may not be. The Southeast Health District's form advises checking local zoning and covenants. Lowndes County's process asks for a zoning approval letter. Ask the city or county building and zoning office what else the lot needs.
Is this what Southern Grind Solutions charges?
No. These are Lowndes County's posted permit fees, not our price list. Each county health department quotes its own fee. We look at the job and put the quote in writing: call or text (912) 381-6261.
Request a Quote

Get In Touch With Southern Grind Solutions

Building a house or moving into a mobile home? Call or text (912) 381-6261 or use the form, and tell us which county the job is in.

Request a Quote

Tell us about the new septic system, the land to clear or the dirt work and where it is. We look at the job and put the quote in writing.

Call (912) 381-6261