Septic Tank Size in Georgia: What Size Tank Does Your Home Need?
In Georgia, a single family home with one to four bedrooms needs a septic tank of at least 1,000 gallons. Add 250 gallons for each bedroom over four. If the home will use a garbage disposal, the tank size goes up by 50 percent. The state’s rules call a disposal a “garbage grinder.”
That is the Georgia Department of Public Health’s septic rule, DPH 511-3-1-.05(3). The County Health Department applies it through the construction permit for a new system.
| Bedrooms | Minimum septic tank size | With a garbage disposal |
|---|---|---|
| 1 to 4 | 1,000 gallons | 1,500 gallons |
| 5 | 1,250 gallons | 1,875 gallons |
| 6 | 1,500 gallons | 2,250 gallons |
| 7 | 1,750 gallons | 2,625 gallons |
How do you figure the septic tank size for your house?
The math takes four steps, the same steps a septic tank size calculator runs.
- Count the bedrooms. Use the rooms the building plan shows as bedrooms.
- Start at 1,000 gallons. That covers one, two, three or four bedrooms.
- Add 250 gallons for each bedroom over four.
- Add half for a garbage disposal. Multiply by 1.5. A five bedroom home with a disposal needs 1,875 gallons.
Sizing the tank is one part of a new system. Our page on septic tank installation covers the rest of the work. That means the dig, setting the tank, the drain field lines, backfill and rough grade.
Why does Georgia count bedrooms, not bathrooms or people?
Georgia’s septic manual bases the sewage flow for a home on its number of bedrooms. The rules define a bedroom as any room intended primarily for sleeping, as shown on the building plan. Bathrooms are not part of the formula.
For design, the state assumes two people per bedroom at 75 gallons per person a day. That comes to 150 gallons per bedroom per day. A DPH note on peak flow cites EPA’s typical use of about 120 gallons a day per bedroom. That is two people at 60 gallons each. The gap between 120 and 150 covers heavy days, such as a house full of holiday guests.
Is a 1,000-gallon septic tank big enough?
For one to four bedrooms with no garbage disposal, yes. A 1,000-gallon tank meets Georgia’s minimum for that home. Add a disposal and the same house needs 1,500 gallons.
DPH rule 511-3-1-.03(5) sets the range for a conventional or chamber system. Its tank design capacity must be at least 1,000 gallons and no more than 10,000.
A precast concrete tank also needs at least 36 inches of liquid depth. It needs at least nine inches of freeboard, the air space under the lid. For published market ranges by tank size, see our guide to septic tank installation cost.
When does a Georgia home need a 1,500-gallon tank?
Two kinds of homes land on 1,500 gallons under the state rule:
- A six bedroom home with no disposal. That is 1,000 gallons plus 250 for each of the two bedrooms over four.
- A one to four bedroom home with a garbage disposal. That is 1,000 gallons plus 50 percent.
Why does a disposal add so much? EPA says food waste can add an unnecessary amount of solid material. It also says a tank with a disposal will need to be pumped more often.
What does Georgia require inside the tank?
- Two compartments. The first holds at least two thirds of the liquid capacity. In a 1,000-gallon tank, that is at least 667 gallons.
- Retention time. Septic tanks must provide at least 24 hours of retention.
- An outlet filter. An approved effluent filter goes on the outlet end of the tank.
- Room for sludge. The state manual says sludge and scum collect in the tank over a few years, usually 3 to 5.
Does the tank material change the size?
The minimum stays the same. EPA says a septic tank is usually made of concrete, fiberglass or polyethylene. Georgia’s manual sets the same 1,000-gallon minimum for concrete and fiberglass tanks. Its polyethylene standards point back to the same capacity rule, 511-3-1-.05(3).
DPH’s onsite sewage page lists approved concrete septic tank manufacturers and approved plastic and fiberglass septic tank manufacturers.
Where can the septic tank sit on your lot?
DPH rule 511-3-1-.05(2) sets the distances. A septic tank may not sit closer than:
- 50 feet to existing or proposed wells, springs, sink holes or suction water lines
- 25 feet to lakes, ponds, streams and other water
- 15 feet to a drainage ditch or embankment
- 10 feet to a property line
The rule also says the tank should sit at least 10 feet from hardscape, drives, swimming pools and building foundations. It recommends at least six inches of earth cover over the tank. After a site inspection, the County Board of Health may allow shorter distances or require longer ones.
On a wooded or overgrown lot, the tank and drain field area get cleared first. Our site preparation work handles the clearing and the rough grade, with the septic system in the same job.
How big does the drain field need to be?
The drain field is sized separately from the tank. Georgia’s Table 10.F sets the trench bottom area from the bedroom count and the soil’s perc rate, in minutes per inch.
- At 5 minutes per inch: 125 square feet of trench bottom per bedroom
- At 30 minutes per inch: 250 square feet per bedroom
- At 60 minutes per inch: 335 square feet per bedroom
A 3 bedroom home on soil that percs at 30 minutes per inch needs 750 square feet of trench bottom. At 60 minutes per inch, it needs 1,005 square feet. Soil slower than 90 minutes per inch is not considered for a conventional system on sites under 3 acres. On 3 acres or more, the line is 120.
The number of trenches, the length of each and the total trench bottom area must match the permit. Our guides to the perc test and chamber vs gravel septic systems cover the soil test and the trench choices.
Who decides your septic tank size?
The state rule sets the minimum, and the County Health Department applies it. DPH rule 511-3-1-.03(2) requires a construction permit from that office before work starts on a lot that will use septic. The permit application lists the number of bedrooms in the dwelling.
The county inspector checks that the tank went in as the permit and the state rules require. The tank must stay visible for that inspection, before any backfill. Our septic tank permit guide walks through each step.
Putting a mobile home on a lot? The county sizes every system on the permit from the bedroom count. Our page on mobile home pads covers the built-up, graded pad that sheds water from under the home.
How often does a septic tank need pumping?
EPA says household septic tanks are typically pumped every three to five years. Its major factors are household size, total wastewater, the volume of solids in the wastewater and septic tank size. A garbage disposal means more frequent pumping. A pumping company does that work, and Southern Grind Solutions installs new septic systems.
How do you get a new septic tank sized and installed?
Southern Grind Solutions installs new septic tanks and drain fields for houses, mobile homes and new builds. We work about 80 miles around Broxton, Georgia.
We look at the job and put the quote in writing. See our page on new septic tank and drain field installs, or call or text (912) 381-6261.