Septic vs Sewer in Georgia: Which One Does Your Lot Need?
In Georgia, distance mostly decides septic vs sewer. The Georgia Department of Public Health’s septic rule, DPH 511-3-1-.03, draws the line at 200 feet. When public or community sewer is available within 200 feet of the property line, the rule requires a connection. The same holds when sewer is available in a public right-of-way abutting the property.
If sewer is not available, the house or mobile home needs an approved septic system. That system needs a construction permit from the County Health Department before work on the lot starts. Where you do get a choice, such as a town lot against a rural one, compare cost and upkeep.
| Septic system | City sewer | |
|---|---|---|
| When the state requires it | Public or community sewer is not available | Sewer within 200 feet of the property line, or in an abutting public right-of-way |
| Who approves it | The County Health Department (permit, then final inspection) | The city or utility that runs the sewer |
| Up-front cost | Soil evaluation, county permit and the system | City tap fee and meter, plus a plumber’s hookup (Tifton: $690 for a 4-inch sewer tap) |
| Monthly cost | No sewer bill | A sewer bill every month (Tifton: $51.65 for a sewer-only home, figured on 7,500 gallons) |
| Upkeep | Pumping every 3 to 5 years, an inspection at least every 3 years (EPA) | No tank on the lot to pump |
| Room on the lot | Georgia’s manual recommends at least half an acre on public water, one acre with a well | Smaller lots: Douglas allows 7,200 square foot subdivision lots on public sewer |
The city figures are market examples from posted city fees and codes, not our price list.
When does Georgia require you to connect to sewer?
Sewer available within 200 feet of the property line, or in an abutting public right-of-way, means a hookup. Those 200 feet run to the property line, not to the house. The rule covers any building, residence or property meant for people to live in or gather.
If an existing septic system fails and sewer is available, the rule calls for immediate connection. A failing residential system under 2,000 gallons a day may be exempted. Its repair or replacement must meet the state’s septic manual. The County Board of Health must also find enough area and usable soil.
For your own lot, the city that runs the sewer and the County Health Department have the final word.
What does a septic system take on a lot without sewer?
On a rural lot without sewer, septic tank installation follows a set order under Georgia’s rules.
- The application. The owner or the owner’s agent applies in writing, on forms from the County Board of Health. The board approves or turns down a complete application within 20 days.
- The soil. A permit comes only after a site inspection finds the soil, groundwater and rock favorable. A soil classifier or another professional the state approves does the soil evaluation. Our guide to the perc test covers that step.
- The clock. A construction permit stays valid for no more than twelve months.
- The final inspection. No backfill and no use until the county inspects the system and approves it in writing.
Our septic tank permit guide walks through each step. On a wooded or overgrown lot, site preparation plans the clearing and the rough grade around the system.
Which costs more, septic or sewer?
Up front, sewer means city fees plus a plumber. Tifton’s posted fee schedule lists $690 for a 4-inch sewer tap. Valdosta sells water and sewer service as a package. There, the owner’s plumber pays the meter and tap fee at the city’s Inspections Department before the hookup.
Up front, septic means the soil evaluation, the county permit and the system itself. For published market ranges, see our guide to septic tank installation cost.
Month to month, sewer is a bill. In Tifton, a home with city sewer but no city water meter pays $51.65 a month, figured on 7,500 gallons. That comes to about $620 a year. Those rates took effect January 1, 2023.
A septic system has no monthly sewer bill. Its costs come every few years instead. EPA says household septic tanks are typically pumped every three to five years. It says the average household system should be inspected at least every three years by a septic service professional.
How much room does each one need?
Georgia’s septic manual recommends minimum lot sizes to county boards of health. For a typical 3 or 4 bedroom home on public water, it lists 21,780 square feet, about half an acre. With a private well, it lists 43,560 square feet, one acre. The same sizes apply to mobile, stick built and modular homes. County boards and county zoning offices may require larger lots.
Sewer lots can be much smaller. In Douglas, the city’s code lets a subdivision lot on public sewer be as small as 7,200 square feet. A Douglas lot on septic with city water needs at least 15,000 square feet.
What about mobile homes and subdivisions?
A mobile home on its own lot follows the same rule as a house. Without sewer close by, the home needs an approved septic system, with the county permit first.
Subdivisions and mobile home parks have a wider line. They can be approved on septic only when no public or community sewer is available within 500 feet. Our page on mobile home pads covers the built-up pad that drains water away from under the home.
How can you tell if a house is on septic or sewer?
EPA lists a few clues on its septic questions page:
- The utility bill. A home on septic shows a $0.00 sewer charge, or gets no utility bill.
- The records. The deed, building permit and design plans will likely show it.
- The yard. Follow the plumbing out of the house to find an access riser, a black or green disc. The tank usually sits about 10 feet from the building.
- The water line. No meter usually means a private well, which often goes with septic.
- The location. A home in a rural area has a high likelihood of septic.
Still not sure? EPA points you to the local health or environmental department.
Who does what?
- The city or utility runs the sewer and sets the tap fee.
- A plumber makes the sewer hookup.
- The County Health Department permits a septic system and makes the final inspection.
- A soil classifier or another approved professional evaluates the soil.
- The installer builds the septic system to the permit.
- A pumping company pumps the tank on the schedule above.
How do you get a written quote for a new septic system?
Southern Grind Solutions installs new septic tanks and drain fields about 80 miles around Broxton, Georgia. The work covers the dig, setting the tank, the drain field lines, backfill and rough grade.
We look at the job and put the quote in writing. Our page on new septic tanks and drain fields around Broxton covers the work. Call or text (912) 381-6261.